Bid contents at a glance
| Section | What the bid should identify |
|---|---|
| Project identity | Property, proposed ADU type, approximate area and proposal date. |
| Documents used | Drawing titles, issue dates, revision numbers, specifications and written scope. |
| Included services | Design, engineering, permit coordination and construction responsibilities. |
| Site work | Access, protection, demolition, excavation, grading, drainage and restoration assumptions. |
| Utilities | Electrical, water, sewer, gas if applicable, communications, trenching and service upgrades. |
| Building work | Foundation, structure, envelope, interior systems, equipment and finishes. |
| Allowances | Defined items, amounts, basis and adjustment method. |
| Owner responsibilities | Purchases, selections, access, approvals, fees and separately retained professionals. |
| Exclusions and unknowns | Work not included and conditions that require further investigation. |
| Price and schedule basis | Price type, proposal validity, anticipated duration and stated dependencies. |
This is a content checklist, not a legal determination that a bid has become a complete home improvement contract. CSLB publishes separate requirements and consumer guidance for the written agreement.
Five things commonly left unclear
- Which plans were priced. “Per plans” is incomplete if the proposal does not identify the plan set and revision.
- Where utility work stops. Interior plumbing and electrical do not necessarily include trenching, main-house work, meters or provider charges.
- What an allowance buys. A dollar amount alone does not identify the assumed quantity, quality, labor or adjustment method.
- Which work remains with the Owner. “Owner supplied” may refer only to purchasing the item or may also exclude delivery, installation and connections.
- Which unknowns can change the price. Existing foundations, concealed conditions, service capacity and access may need investigation before a firm scope is possible.
Identify the project and drawing basis
The proposal should be traceable to one version of the project. Record the property, ADU type, approximate floor area and the date of the bid. List the architectural, structural, energy and other documents used, including revision dates where available.
If drawings are incomplete, the bid should state which assumptions fill the gaps. For a garage conversion, that may include assumptions about the existing slab, framing, roof and legal condition. For a detached ADU, it may include foundation type, building location, access and utility routes.
| Item | Question |
|---|---|
| Architectural plans | Which sheet set and revision were used? |
| Structural information | Is engineering complete, assumed or excluded? |
| Finish information | Are selections specified, carried as allowances or not priced? |
| Agency corrections | Who prices and incorporates revisions after plan check? |
Separate site work and utility work
ADU construction affects more than the building footprint. The bid should describe access, temporary protection, demolition, hauling, excavation, grading, drainage and restoration of disturbed areas. If landscaping, fences, driveways or hardscape will be removed, state who restores them.
For each utility, identify the starting point, route, connection and known capacity assumption. Separate work performed by the Contractor from fees or work controlled by an agency or utility provider.
| Area | Scope to clarify |
|---|---|
| Electrical | ADU wiring, feeder, panels, service-capacity assumptions, upgrades, meter arrangement and trenching. |
| Water | Pipe route, connection point, shutoff, meter assumptions and provider work. |
| Sewer | Route, connection, cleanouts, trenching, existing lateral assumptions and restoration. |
| Gas | Whether gas is part of the design and which connection or meter work is included. |
| Drainage | Roof drainage, grading, required collection or conveyance work and affected surfaces. |
| Access | Equipment access, material staging, protection, temporary removal and repair. |
Do not treat “utilities included” as a complete answer. Ask the bidder to mark included, excluded or unresolved for each row.
Describe the building systems and finish basis
The proposal should identify the major work used to produce a complete ADU: foundation, framing, roofing, exterior finish, windows and doors, insulation, drywall, plumbing, electrical, heating and cooling, ventilation, cabinets, counters, flooring, paint, fixtures and equipment.
Not every bid needs a price beside every trade. For a lump-sum proposal, the important question is whether the work and material basis are sufficiently defined. CSLB’s contract guidance emphasizes describing how the work will be performed and which products and materials will be used. The bid is where those details should begin becoming visible before contract review.
| Weak description | More useful description |
|---|---|
| Windows included | Window material, performance or specified schedule, operation types and installation scope. |
| Kitchen included | Cabinet basis, countertop basis, sink, faucet, appliances, installation and connections. |
| Flooring allowance | Covered area, material allowance, tax and delivery basis, installation and adjustment method. |
| Paint included | Interior and exterior areas, preparation, finish system and excluded specialty coatings. |
Make allowances and Owner items explicit
An allowance is an amount inside the price for a defined item that will be selected or finally priced later. Identify the covered item, amount, assumed quantity or product level, whether tax, delivery, labor and markup are included, and how overages or unused amounts will be handled.
An Owner-purchased item needs more than a shopping assignment. Record who verifies the model, who orders it, when it must arrive, who receives and stores it, who installs it, who makes the connections and who handles damage or returns.
List exclusions, unknowns and schedule conditions
An exclusion should be specific enough to assign responsibility or add a separate budget. An unresolved condition should identify what information is missing, who obtains it and how the result may affect scope, price or time.
The schedule should explain what starts the duration. “Four months” may mean four months after permits, after site mobilization or after all Owner selections arrive. Identify required decisions, long-lead items, agency work and other dependencies instead of treating the duration as an unconditional completion promise.
| Bid status | How to handle it |
|---|---|
| Excluded | Assign the work, obtain a separate price or remove it from the intended project. |
| Allowance | Confirm the amount and reconciliation rules. |
| Unresolved | Define the investigation, responsible party and decision point. |
| Optional alternate | Keep the separate price and state whether it is accepted. |
Common warning signs
- No property, proposal date or drawing revision is identified.
- Large parts of the project are covered by one phrase such as “complete ADU.”
- Required-looking work is neither included nor excluded.
- Allowances have no quantity, quality or adjustment basis.
- Owner-supplied items do not assign installation and connection responsibilities.
- Utility and site work stop at an undefined point.
- Clarifications exist only in calls or text messages.
- The proposal expires before the Owner can reasonably investigate important open items.
These are clarity problems, not automatic findings of misconduct. Ask the bidder to revise or clarify the proposal in writing.
When a bid is not ready to rely on
Treat the bid as an early budget rather than a comparable proposal if it lacks a common drawing basis, leaves major site or utility work undefined, or cannot distinguish included scope from assumptions. The project may genuinely need more design or investigation before those answers are possible.
A detailed bid also is not automatically a complete or compliant construction contract. The final agreement needs separate review for required notices, payment terms, dates, changes, responsibilities and other applicable terms. CSLB’s home improvement contract materials are the official consumer starting point.
What to do next
- Mark every section as included, allowance, excluded or unresolved.
- Ask the bidder to identify the exact drawing revision.
- Resolve the site, utility and Owner-purchase questions with the largest budget effect.
- Request one dated revision that incorporates accepted clarifications.
- Use the same scope questions with the other bidders.
- Compare the bids, then carry the selected scope into contract review.
Open the ADU quote-basis checklist or continue to How to compare ADU Contractor bids in Los Angeles.
Questions, answered
Does an ADU bid need a line-item cost for every trade?
Not necessarily. A lump-sum proposal can still be useful if it clearly defines the included scope, drawings, allowances, exclusions, responsibilities, schedule assumptions and circumstances that may change the price.
Link to this answerShould permit fees and utility fees be included?
The proposal should state whether each fee is included, excluded, paid directly by the Owner or not yet known. Do not assume that permit processing includes agency fees or that utility work includes provider charges.
Link to this answerWhat should an ADU allowance identify?
Identify the item, amount, assumed quantity or product level, which costs are included, what supporting records will be used and how overages or unused amounts will be adjusted.
Link to this answerOfficial sources
Official references checked on . This guide uses contract guidance to identify information that should become clear during bidding; it does not claim that a bid and a final contract are the same document.
| Source | Used for |
|---|---|
| CSLB: Finding the right licensed Contractor | Using identical plans, specifications and scope when comparing written bids. |
| CSLB: What is a home improvement contract? | Detailed work and material descriptions, payment schedule, permits, completion date and written changes. |
| CSLB: Homeowner contract checklist | Permit responsibility, fees, dates, detailed work, materials, payments and written changes. |
Prepared for PrepareToBuild.info as an editorial draft, assisted by AI. Not yet reviewed by a licensed construction or legal professional. Scope categories are educational prompts, not a representation that every project requires the same work. Confirm project requirements with the responsible agency and qualified professionals.